Home Concept Technology Budget About


Category Item Amount Cost Total
Hardware low-end computer 8 $500 $4,000
high-end computer 1 $1500 $1,500
cameras 9 $100 $900
projector 4 $1500 $6,000
networking equipment 1 $500 $500
100" projection glass 10 $800 $8,000
misc. hardware 1 $500 $500
Software OS 9 $80 $640
Subtotal $18,040


Category Item Hours Cost/Hour Total
labor(software deveopment) overhead tracking 10 60 $600
wall tracking 40 60 $2,400
head reconstruction 50 60 $3,000
rendering 70 60 $4,200
modelling 50 60 $3,000
networking 50 60 $3,000
streaming 50 60 $4,200
integration 80 90 $7,200
labor(manual labor) site intstallation 400 25 $10,000
glass preparation 20 25 $500
Subtotal $38,100
Total $56,140


Phase Days
Software development 9 weeks
Site installation 2 weeks
Testing/finalization 1 week
Total 12 weeks